What Is Demurrage in Shipping?
Demurrage is the compensation a charterer pays the shipowner when a vessel is kept at the load or discharge port longer than the laytime agreed in the charter party. On a clean tanker it is a fixed daily rate, paid pro rata by the hour, so small delays add up fast.
Vessel demurrage is different from container demurrage and detention. In tanker trading it sits between three contracts: the charter party, your purchase contract and your sales contract. If they do not match, you pay the owner and cannot pass the cost on.
How to Calculate Laytime and Demurrage
Laytime usually starts when a valid notice of readiness (NOR) is tendered, plus the notice time in the charter party (often six hours), or when the vessel is all fast if earlier. It ends when the hoses are disconnected. Shifting, vessel faults and agreed exceptions are deducted.
| Worked example (fictitious) | Value |
|---|---|
| Vessel and rate | MR tanker, USD 30,000 per day |
| Laytime allowed | 48 hours |
| Planned probability of demurrage | 74%, P90 exposure USD 17,047, MEDIUM |
| Actual time on demurrage (SOF) | 24.3 hours = USD 30,375 |
| Not recoverable from the buyer | USD 9,025 |
| First deadline | Buyer notice in 30 days, before the owner's claim deadline |
Where Demurrage Money Leaks
- Unplanned waiting because the berth, shore tanks or inspector were not ready.
- Laytime counted wrongly: notice time, shifting or half-rate events missed.
- Weak statements of facts that cannot prove a claim.
- Claims lost to time bars.
- Costs you cannot pass on because the contracts do not match.
Inside the Planner
| Tab | What it does |
|---|---|
| Call Plan | Expected timeline, laytime used and remaining, exposure and cost of delay |
| Risk Drivers | 14 delay causes with min, likely and max hours; probability, P90, worst case and rating |
| Mitigation | Actions ranked by net saving |
| SOF Laytime Calc | Up to 60 periods; the exact minute laytime ran out and demurrage owed |
| Pumping Performance | 24-hour or 100 psi warranty tested against the pressure log |
| Contract Chain | What you can recover from buyer and seller |
| Claim & Time Bar | Deadlines and a 12-document checklist |
| Lists | Counting rules, preset to typical Asbatankvoy terms |
Laycan vs Laytime, and How to Reduce Demurrage
Laycan is the window in which the vessel must arrive and tender NOR; laytime is the time allowed to load or discharge once it is there.
- Book the berth window and confirm shore tank space early
- Pre-appoint the inspector
- Check the pumping warranty and keep an hourly pressure log
- Record every delay in a signed statement of facts
- Align laytime and rates across the charter party and both sales contracts
Who It Is For
Fuel exporters, charterers, traders and terminal coordinators handling EN590 diesel, jet fuel, gasoline or fuel oil cargoes.
Save With a Bundle
Fuel Trading Operations Bundle
$4976 tools for freight, Worldscale, demurrage, pipelines and rack margins (value $894).
See what is included →Master Fuel Trading Toolkit
$1,49726 fuel trading tools, including the Operations Command Center (value $3,424).
See what is included →Hyvnd All-Access
$1,997Every Hyvnd fuel and SAF tool, all 45 tools (value $5,956).
See what is included →Institutional Fuel Deal Execution – Private Mentorship
Move from scattered industry information to a disciplined institutional execution path, with better clarity, documentation flow and mandate positioning.
- Full institutional fuel deal curriculum: from mandate positioning to deal progression and closing structure
- ICPO, LOI, FCO and SPA templates and checklists for deal readiness
- Guided review of your live deal pipeline: what is credible, what is weak and what needs restructuring
- Mandate positioning, refinery and trader communication, plus deal triage to filter fake offers
- All 3 programs: Foundations Fuel Trade ($497), Global Fuel Trade Vault ($1,497) and the Private Mentorship ($7,500)
- Every Hyvnd tool (refinery, SAF and beginner) with step-by-step walkthrough videos
- 1 year of fuel deal execution support and private access to updates
Demurrage & Laytime: Frequently Asked Questions
What is demurrage in shipping?
The money a charterer pays the shipowner when a vessel stays at port longer than the agreed laytime, usually a daily rate paid pro rata.
How is laytime calculated?
From valid NOR plus notice time (or all fast, if earlier) until hoses off, minus excluded periods. Demurrage = (laytime used − allowed) ÷ 24 × daily rate.
What is the difference between laycan and laytime?
Laycan is the arrival window; laytime is the time allowed to load or discharge.
How can I reduce demurrage costs?
Plan the berth window, confirm shore tanks and inspector early, check the pumping warranty, keep a signed SOF and align all three contracts.
Which charter parties does it support?
It is preset to typical Asbatankvoy rules and covers Shellvoy-style wording; you set the counting rules per charter party.
Is this legal advice?
No. Contract wording decides how laytime and demurrage are counted. Example figures are fictitious.
Plan it, prove it, claim it
One avoidable demurrage day can cost more than this planner many times over.
Educational and operational tool. Not legal advice. Contract wording decides how laytime and demurrage are counted. Example figures are fictitious.